Route 340 (Palisades S5)



This year, leaf removal operations will begin on 10/30/2023. The estimated schedule for this road is listed below.

Round 1

Scheduled: Week starting Oct. 30, 2023
Status: Completed
Completed on: 11/01/2023

Round 2

Scheduled: Week starting Nov. 20, 2023
Status: Completed
Completed on: 11/27/2023

Round 3

Scheduled: Week starting Dec. 11, 2023
Status: Completed
Completed on: 12/16/2023